Chanterlands Avenue road works

John Fareham and John Abbott have secured the postponement of road works being carried out on Chanterlands Avenue by Northern Power Grid until essential repairs to the County Road North flyover have been completed.

A number of local residents have drawn our attention to the fact that one lot of road works at any given time may be acceptable, but two lots look more like gridlock in the offing.  We therefore contacted the officers who got on to Northern Power Grid. They in turn agreed that all their works on Chanterlands Avenue would stop, whether completed or not, and the road would be fully opened before County Road North was closed down for repairs and work on Chanterlands Avenue would not resume until work on the flyover was complete.