John Fareham and John Abbott have news regarding the likely reopening date of County Road North being earlier than at first anticipated.
We have had concerns about the duration of the work and the effect on traffic raised by local residents and even by our colleagues across the Hull-Cottingham boundary. We are therefore pleased to announce that we have been told by the officers that the damaged concrete has now been removed from the flyover. This not only gave the engineers a rough idea of how much work needed to be done but also ideas as to how, albeit at increased cost, they could arrange for some of the repairs to be done with the bridge re-opened to traffic. As a result the flyover is expected to be open to traffic again by around 13/14 October.